City of Sequin header
File #: 20-220    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/23/2020 In control: City Council
On agenda: 7/7/2020 Final action: 7/7/2020
Title: Resolution approving a $183,769,179.00 project to decommission the Walnut Branch Wastewater Treatment Plant through the construction of a sanitary sewer lift station, two sanitary sewer force mains, an expansion of the Geronimo Creek Wastewater Treatment Plant to 12.0 million gallons per day, and the demolition of the existing Walnut Branch Wastewater Treatment Plant; and declaring an effective date - Tim Howe, Director of Water/Wastewater Utilities
Attachments: 1. Council Memo - WBWWTP Decommissioning Project 07-07-2020.pdf, 2. Resolution approving the Walnut Branch Wastewater Treatment Plant decommissioning

Title

Resolution approving a $183,769,179.00 project to decommission the Walnut Branch Wastewater Treatment Plant through the construction of a sanitary sewer lift station, two sanitary sewer force mains, an expansion of the Geronimo Creek Wastewater Treatment Plant to 12.0 million gallons per day, and the demolition of the existing Walnut Branch Wastewater Treatment Plant; and declaring an effective date - Tim Howe, Director of Water/Wastewater Utilities