File #: 17-243    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/10/2017 In control: City Council
On agenda: 9/5/2017 Final action: 9/5/2017
Title: Resolution authorizing the City Manager to execute change order #2 in the amount of $146,357.00 and change order #3 in the amount of $95,247.40 to the River-San Marcos-Heideke Phase II Project to Atlas Construction Corporation contract - Jose (Joe) R. Ramos, Jr., P.E., City Engineer
Attachments: 1. Memo to Council_RSMH PH II_CO#2_CO#3_09052017, 2. RSMH PH II_CO #2, 3. RSMH PH II_CO #3, 4. CCMap_drainage_Sept2017_ver2, 5. CCMap_water_Sept2017_ver2, 6. Resolution approving change order 2 for the RSMH-Phase II Project

Title

Resolution authorizing the City Manager to execute change order #2 in the amount of $146,357.00 and change order #3 in the amount of $95,247.40 to the River-San Marcos-Heideke Phase II Project to Atlas Construction Corporation contract - Jose (Joe) R. Ramos, Jr., P.E., City Engineer